最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)

Article 12

In force

因承包人的原因造成建设工程质量不符合约定,承包人拒绝修理、返工或者改建,发包人请求减少支付工程价款的,人民法院应予支持。

Judicial Interpretations · Supreme People's Court · In force from January 1, 2021

Article 11Back to full textArticle 13

Texts on this site are reproduced from theParty Regulations Library on 12371.cn, theNational Database of Laws and Regulations(General Office of the NPC Standing Committee), and the official libraries of the State Council departments: STA Policy and Regulations Library, MOHRSS Rules Library, MEE Rules Library, MOE Rules Library, MCT Departmental Rules, NRTA Rules Library, MEM Rules Library. Party regulations and national law are two separate bodies of rules: this site searches them separately and never merges the results. Departmental rules and normative documents rank below laws and administrative regulations and are likewise kept in their own corpus.

Where an electronic text differs from the standard text of the law, the standard text governs. All texts here are in Chinese, the language in which they were officially promulgated; this interface is translated but the legal texts are not. The content of this site is for reference only and does not constitute legal advice— consult a practising lawyer about any specific matter.